Question: MC Qu . 0 9 - 2 3 The project manager bullding a . . . The project manager building a new underwater dolphin exhibit

MC Qu.09-23 The project manager bullding a...
The project manager building a new underwater dolphin exhibit at City Aquarium is reviewing the chronological sequence of activities that must be completed on the project and the estimated time of completion of each activity. He is employing
Multiple Choice
a Gantt chart.
a total quality management process.