Question: MC Qu . 1 6 ( Static ) A project scheduler is working on . . . A project scheduler is working on a project

MC Qu.16(Static) A project scheduler is working on...
A project scheduler is working on a project that technically allows three activities to be done at the same time. If they were to be implemented at the same time, the
scheduler would need 5 contractors in order for the activities to be completed on time. There are only 3 available for the project. This is an example of what type of
constraint?
Multiple Choice
Materials
Technical
Peoplesystems involve reporting, controlling, and recording changes to the project baseline.
Multiple Choice
Total management
Change management
Productive management
Drnartivo manariomont
 MC Qu.16(Static) A project scheduler is working on... A project scheduler

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!