Question: MC Qu . 2 2 ( Static ) The amount of time an activity... The amount of time an activity can be delayed and yet
MC QuStatic The amount of time an activity...
The amount of time an activity can be delayed and yet not delay the project is termed
Multiple Choice
total slack.
free slack.
critical float.
float pad.
slip pad.