Question: MC Qu . 6 0 ( Static ) _ _ _ _ _ _ _ _ reserves are identified... _ _ _ _ _ _

MC Qu.60(Static)________ reserves are identified...
________ reserves are identified for specific work packages and are distributed by the project manager and the team members.
Multiple Choice
Contingency
Work package
Incremental
Incidental
Additional