Question: McCombs Contractors received a contract to construct a building for a price of $ 700,000, and the company determined that its performance obligation was satisfied
McCombs Contractors received a contract to construct a building for a price of $ 700,000, and the company determined that its performance obligation was satisfied over time. Other information relating to the contract is as follows:
| 2017 | 2018 | |
| Costs incurred during the year | 150,000 | 242,000 |
| Estimated costs to complete | 350,000 | 168,000 |
| Billings during the year | 120,000 | 250,000 |
| Cash collections during the year | 100,000 | 260,000 |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts