Question: Meals are cooked in a process with two resources. The first resource has a capacity of 28 meals per hour. The capacity of the second
Meals are cooked in a process with two resources. The first resource has a capacity of 28 meals per hour. The capacity of the second resource is 24 meals per hour. The first resource has 9 workers and the second resource has 8 workers. One additional worker is hired who is as productive as the current workers.
Instruction: Round your answer to three decimal places. What is the new capacity of this process?