Question: Meals are cooked in a two-step process with two sequential resources. The capacities of the resources are 28 and 24 meals per hour. How long

Meals are cooked in a two-step process with two sequential resources. The capacities of the resources are 28 and 24 meals per hour.

How long does it take 19 meals to be cooked (in hours)?hour