Question: ment was 3 0 , 0 0 0 cases. The bakery operated 2 5 days per month with 3 Step 1 : Mixing the dough

ment was 30,000 cases. The bakery operated 25 days per month with 3
Step 1: Mixing the dough involves combining the flour, shortening, sugar and cocoa and mixing. The processing time for one case is 50 seconds. There are two operators. Guan counted the inventory at the various storage locations and found ingredients for 1,200 cases of finished cookies before the mixer.
Step 2: Forming, baking and cooling are done by an automated production machine that holds 20 cases operating continuously at the same rate. The machine is able to form, bake & cool 20 cases every 15 minutes. That means 20 are finished every 15 minutes. Guan counted 300 cases of mixed dough before step 2.
Step 3: Guan counted 60 cases waiting to be iced & assembled. Icing and cookie assembly are done in a single operation, with three operators. The processing time is 12 minutes per case. Guan counted 600 cases before step 4.
Step 4: Finally, the processing time for packaging is 90 seconds per case. There is one operator and 60 cases waiting to be shipped.
The Sales department informs the Warehouse about sales forecasts. The Warehouse sends electronic forecasts and daily orders to Production Control. Production Control issues electronic purchase orders to the ingredient and packaging suppliers weekly but provides daily orders to each of the internal departments in the bakery.
Question 1
0.1pts
The available work time = min/day (enter integer).
Question 2
0.1pts
The takt time is seconds (enter integer
).
Question 3: the customer demand is _____ cases/day
 ment was 30,000 cases. The bakery operated 25 days per month

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!