Merry Co. purchased a machine costing $125,000 for its manufacturing operations and paid shipping costs of $20,000.
Fantastic news! We've Found the answer you've been seeking!
Question:
manufacturing operations and paid shipping costs of $20,000.
Merry spent an additional $10,000 testing and preparing the machine
for use. What amount should Merry record as the cost of
the machine?
$155,000
$145,000
$135,000
$125,000