Carol Cagle has a repetitive manufacturing plant producing trailer hitches in Arlington, Texas. The plant has an average inventory turnover of only 12 times per year. He has therefore determined that he will reduce his component lot sizes. He has developed the following data for one component, the safety chain clip:
\table[[Setup labor cost,$25 per hour],[Annual holding cost,$16 per unit],[Daily production,1,008 units/8 hour day],[Annual demand,42,000(250 days each daily demand of 168 un],[Desired lot size,126 units (one hour of production)]]
To obtain the desired lot size, the set-up time that should be achieved = minutes (round your response to two decimal places).
Points: 0 of 1 Carol Cagle has a repetitive manufacturing plant producing

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!