Question: MGMT - 1 0 0 8 Project Management Assignment 5 Dropbox submission Due: Sunday April 1 4 th , 2 0 2 4 Question 1

MGMT-1008 Project Management
Assignment 5
Dropbox submission Due: Sunday April 14th,2024
Question 1 Complete the Arrow on Activity diagram
below:
Question 2
Activity Required Predecessor Normal Time Normal Cost Crash Time Crash Cost
A (None)8 $40006 $6000
B (None)5150042000
C (None)6250043000
D A 4180032000
E A, B 6100051200
F C 7200053000
G A 5300036000
H D, E, F 8450059000
I C 96000410000
J D, E, F 6600048000
K G, H 4200032600
L D, E, F 6300039000
M I, J 48000212000
The scheduled completion time is 25 weeks. You must pay a $1500 penalty for every
week you are late. You get a $1000 bonus for every week you are early.
1. Create an Activity On Node (AoN) network diagram.
2. Find the normal completion time and the critical path.
3. Determine the schedule that minimizes your total cost for this project, including any
penalty or bonus.
a. How did you decide when to stop trying shorter and shorter completion times?
b. How many weeks total should the project take?
c. What will your total cost be?
d. Which activities will be shortened from their normal times, and by how much?
e. Which activities are critical to the least cost schedule?
Question 3
What does PERT stand for?
In a given project, the most optimistic duration is 2 days, most likely duration is 3 days
and the pessimistic duration is 10 days. What is the PERT weighted average?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!