Question: MGMT - 1 0 0 8 Project Management Assignment 5 Dropbox submission Due: Sunday April 1 4 th , 2 0 2 4 Question 1
MGMT Project Management
Assignment
Dropbox submission Due: Sunday April th
Question Complete the Arrow on Activity diagram
below:
Question
Activity Required Predecessor Normal Time Normal Cost Crash Time Crash Cost
A None $ $
B None
C None
D A
E A B
F C
G A
H D E F
I C
J D E F
K G H
L D E F
M I, J
The scheduled completion time is weeks. You must pay a $ penalty for every
week you are late. You get a $ bonus for every week you are early.
Create an Activity On Node AoN network diagram.
Find the normal completion time and the critical path.
Determine the schedule that minimizes your total cost for this project, including any
penalty or bonus.
a How did you decide when to stop trying shorter and shorter completion times?
b How many weeks total should the project take?
c What will your total cost be
d Which activities will be shortened from their normal times, and by how much?
e Which activities are critical to the least cost schedule?
Question
What does PERT stand for?
In a given project, the most optimistic duration is days, most likely duration is days
and the pessimistic duration is days. What is the PERT weighted average?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
