Question: MGMT 1 8 3 - 2 0 2 4 - W - Individual Assignment 0 1 Family Day Event 2 0 2 5 A planning
MGMTW Individual Assignment
Family Day Event
A planning team has determined that this special Family Day event can be decomposed into major deliverables. Note that Family Day is a wellknown annual event, and the date changes slightly depending upon the year in which it occurs. In this case, there are additional days of events
and activities that are also planned these days are in addition to the special events that actually occur on Family Day
Use this information to prepare project schedule for the event. Event is held for days in Peterborough and budget is capped at $
For each major deliverable shown in the WBS prepare an additional key activities minimum for each major deliverable.
Assign Resources for all tasks.
Decompose deliverables into individual activities.
Individual Assignment Instructions:
Network Diagram
Prepare a network diagram for your Family Day Event Remember that a network diagram is used to help you determine the sequence of
events at a high level. Prepare your network diagram using Excel, Word, or Powerpoint. Submit your network diagram in pdf Make sure your pdf
file is formatted correctly and is professional. Do not create your network diagram using MS Project.
Detailed Schedule
Once your Network Diagram is complete, prepare your detailed schedule for the Family Day Event in an MS Project Gantt chart. In that Gantt
chart you will include the following:
Define Activities
Sequence Activities
Define Activity Durations for each task this is your project, so it is up to you to determine the durations for the activities you think are required for
the Family Day Event
Determine the Resource Allocation for each task you determine what skills and people are required to successfully execute your project
Tasks Predecessors
ReferencesCitations etc.
References for this assignment include the following:
All Lecture Notes todate
Textbook "Understanding Project Management"
PMBOK Guide th edition and th edition
You must include references in all of your documentation. For your MS Project file you must also submit a pdf file that has a title page and include
your references as well.
All submissions will also be graded on professionalism.
Additional Requirements
This assignment is due on Sun Feb at in the dropbox "IndivAssign: Family Day"
ONLY Individual Submissions, no group work allowed.
Submissions files are to be in MS Project format and pdf format only. Submissions in other formats will not be accepted.
To summarize: you need to submit one MS Project file, one pdf Network Diagram, and one pdf Cover Page and Citations document.
The following diagram is for your reference in completing this assignment
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock