Question: MGMT 1 8 3 - 2 0 2 4 - W - Individual Assignment 0 1 Family Day Event 2 0 2 5 A planning

MGMT183-2024-W - Individual Assignment 01
Family Day Event 2025
A planning team has determined that this special Family Day event can be decomposed into 8 major deliverables. Note that Family Day is a wellknown annual event, and the date changes slightly depending upon the year in which it occurs. In this case, there are 7 additional days of events
and activities that are also planned (these days are in addition to the special events that actually occur on Family Day).
Use this information to prepare project schedule for the event. Event is held for 7 days in Peterborough and budget is capped at $10,000.
For each major deliverable shown in the WBS, prepare an additional 8 key activities (minimum) for each major deliverable.
Assign Resources for all tasks.
Decompose deliverables into individual activities.
Individual Assignment Instructions:
Network Diagram
1 Prepare a network diagram for your Family Day Event 2025. Remember that a network diagram is used to help you determine the sequence of
events at a high level. Prepare your network diagram using Excel, Word, or Powerpoint. Submit your network diagram in pdf. Make sure your pdf
file is formatted correctly and is professional. Do not create your network diagram using MS Project.
Detailed Schedule
2 Once your Network Diagram is complete, prepare your detailed schedule for the Family Day Event 2025 in an MS Project Gantt chart. In that Gantt
chart you will include the following:
Define Activities
Sequence Activities
Define Activity Durations for each task (this is your project, so it is up to you to determine the durations for the activities you think are required for
the Family Day Event)
Determine the Resource Allocation for each task (you determine what skills and people are required to successfully execute your project)
Tasks / Predecessors
References/Citations, etc.
3 References for this assignment include the following:
All Lecture Notes to-date
Textbook "Understanding Project Management"
PMBOK Guide 6th edition and 7th edition
You must include references in all of your documentation. For your MS Project file you must also submit a pdf file that has a title page and include
your references as well.
All submissions will also be graded on professionalism.
Additional Requirements
4 This assignment is due on Sun 18 Feb at 1200 in the dropbox "IndivAssign01: Family Day"
ONLY Individual Submissions, no group work allowed.
Submissions files are to be in MS Project format and pdf format only. Submissions in other formats will not be accepted.
To summarize: you need to submit one MS Project file, one pdf Network Diagram, and one pdf Cover Page and Citations document.
The following diagram is for your reference in completing this assignment

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!