Question: MGMT 6 0 2 0 CPM practice A network consists of the activities in the following list. Times are given in weeks. Activity Preceding Time

MGMT 6020 CPM practice
A network consists of the activities in the following list. Times are given in weeks.
Activity Preceding Time
A --8
B --3
C A 7
D A,B 3
E C 4
F D 6
* Preceding relationship: Activity A precedes activity C.
Activity A and B precede activity D.
Activity C precedes activity E.
Activity D precedes activity F.