Question: Microsoft Project Exercises Page 1 of 4 Application Development Project Estimated cost - $ 1 0 0 , 0 0 0 Estimated duration 2 0
Microsoft Project Exercises
Page of
Application Development Project
Estimated cost $
Estimated duration weeks US Holiday Calendar hrs weeks
Staff required:
Project Manager Bill $hour
Technical Manager Sue $hour
Developer Drake $hour
Business Analyst John $hour
Materials Required
Laptops @ $ each
Project Processes:
Initiating
o Project CharterKick Off Meeting Hours: Staff: Bill
Planning summary task
o WBS week one
Duration: days Hours: eachday Staff: John, Drake
Executing summary task
o Design week and
Duration: days Hours: each day Staff: Sue, John, Drake
o Design Document created Milestone
o Build App Week to
Duration: days Hours: each day Staff: SueDrake
o App ready for testing Milestone
o Test App
Duration: Week Hours: eachday Staff: JohnDrake
o ChangesFixes after testing
Duration: Week to Hours: each day Staff: SueDrake
App ready for testing V Milestone
o Test App
Duration: Week Hours: eachday Staff: JohnDrake
App ready for Go Live Milestone
Monitor and Control
Closing
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock