Question: Mike has four assignments due in class tomorrow. Classes start at 8am (Marketing 304), 10am (OM 385), 1pm (Finance 216), and 3:30pm (Psych 200). Each
Mike has four assignments due in class tomorrow. Classes start at 8am (Marketing 304), 10am (OM 385), 1pm (Finance 216), and 3:30pm (Psych 200). Each class lasts one hour and Mike has no other classes. It is now midnight, and Mike estimates that the finance, OM, marketing, and psych assignments will take him six, three, four, and two hours, respectively. Which sequencing method (EDD or SPT) enables Mike to get everyone done on time?
A. EDD - Earliest Due Date
B. SPT - Shortest Processing Time