Question: (minimizing idle time accomplishes the same task as minimizing make-time) 11. Given the operation times in the two-work-centre flow shop below: a. Develop a job

 (minimizing idle time accomplishes the same task as minimizing make-time) 11.

(minimizing idle time accomplishes the same task as minimizing make-time)

11. Given the operation times in the two-work-centre flow shop below: a. Develop a job sequence that minimizes total idle time at Work Centre 2. b. Construct a load Gantt chart for the activities at the two work centres, and determine work centre 2's idle time. LO3 Job Times (minutes) A B CD EF Work Centre1 20 16 43 60 35 42 Work Centre 2 27 30 51 12 28 24