Question: Mixers Ltd is engaged in producing a standard mix using 60 kg of Chemical X and 40 kg of Chemical Y. The standard loss of
Mixers Ltd is engaged in producing a standard mix using 60 kg of Chemical X and 40 kg of Chemical Y. The standard loss of production is 30%. The standard price of X is Rs. 5 per kg and Y Rs. 10 per kg. The actual mix and yield were as follows:
X 80 Kg @ Rs. 4.50 per Kg
Y 70 Kg @ 8.00 per Kg
Actual Yield 115 Kg
Calculate Direct Material Cost, Price, Usage, Mix and Yield Variances.