Question: Mod 2 In Class Assignment: Calculate Labor Calculate the direct cost of labor for a project team member using the following data: Hourly rate: $

Mod 2 In Class Assignment: Calculate Labor
Calculate the direct cost of labor for a project team member using the following data:
Hourly rate: $50hr
Hours needed: 120
Overhead rate: 40%
2. The Munsters have been saving money in order to buy a house. They figure that given current interest rates they could afford a $400,000 home. Before looking at houses on the market they decide to explore the possibility of building a new home. The Munsters figure they could buy a suitable lot for $70,000-$75,000. At a minimum they want to build a 2,300 square-foot house. The cost for a house of the quality they desire is $160 per square foot. Given this information should the Munsters pursue the option of building a new house?
3. Below is a project WBS with cost apportioned by percent. If the total project cost is estimated to be $800,000, what are the estimated costs for the following deliverables? A: Design, B: Programming, C: In House Testing
What weaknesses are inherent in this estimating approach?
 Mod 2 In Class Assignment: Calculate Labor Calculate the direct cost

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!