Question: Model the following problem as LP and solve it: A manufacturing facility requires the production plan to satisfy the demand for the following 5 months.

Model the following problem as LP and solve it:

Model the following problem as LP and solve it: A

A manufacturing facility requires the production plan to satisfy the demand for the following 5 months. Production cost is $3/unit, while inventory cost is $1/unit per month. The facility has a capacity of 300 units per month. Demands are summarized in the following table. Month Demand 250 150 300 2 400 400