Question: Modifications are ignored when Planning Optimization is run again. Modifications are included when Planning Optimization is run again. Approved orders are automatically firmed. Approved orders

Modifications are ignored when Planning Optimization is run again.
Modifications are included when Planning Optimization is run again.
Approved orders are automatically firmed.
Approved orders are set to unprocessed.
Approved orders are set to completed.