Question: Module 6 Case Study Controlling Project Risks Student Name:________________ Date:________________________ Now the project is well underway, with several challenges being properly addressed.You just received an

Module 6 Case Study

Controlling Project Risks

Student Name:________________

Date:________________________

Now the project is well underway, with several challenges being properly addressed.You just received an email message from the electrical contractor outlining a 3-week delay in the Install and Terminate Electrical Devices activity, due to defective material.

The electrical contractor's SOW states that if there is a potential delay, all subcontractors must inform you in writing within 48 hours of the onset of the delay, and the email message meets this requirement.

The project has already been significantly delayed due to severe weather conditions. Although your risk analysis included a schedule contingency for weather conditions and the receipt of defective materials, this is a serious problem that threatens to further delay the project.

  1. Once the issue is resolved, you and the team continue to examine the project results over time to determine if performance is improving or worsening. Which analysis process should you use and how is it done?

Answer:

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!