Answer ALL the following questions and upload your answers to Question 1 in Blackboard. Show all your work. Remember that you may only submit one document that includes all of your answers. Complete all the YELLOW CELLS to develop an MRP record for items B, C, and D. If the answer is 0, you can either put 0 or leave the cell blank.
Bill of Materials (BOM):
Master Production Schedule (MPS) for Item A:
| Week | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 |
| Qty Needed (FAS) | 0 | 100 | 0 | 200 | 0 | 120 | 180 | 60 | 0 | 0 |
Item Master File (IMF):
| Item | B | C | D |
| Lot Sizing Rule | POQ (P=3 weeks) | L4L (lot for lot) | FOQ (Q* = 500) |
| Lead Time (LT) | 1 week | 2 weeks | 3 weeks |
| Scheduled Receipts (SR) | None | 200 in week 1 | None |
| Beginning On-Hand (OH) Inventory | 20 | 0 | 425 |