Question: Mokthar Company allocates manufacturing overhead costs using machine hours and the normal costing method. The following data are available for 2014 Budgeted manufacturing overhead cost
Mokthar Company allocates manufacturing overhead costs using machine hours and the normal costing method. The following data are available for 2014 Budgeted manufacturing overhead cost $1,050.000 Budgeted machine-hours 15,000 Actual manufacturing overhead cost $1,200,000 Actual machine-hours 12,000 The direct manutacturing costs of Job 65 equal $50,000. Job 65 used 300 machine hours in 2014, Required Compute the overhead under or overallocated 2 Marks)