Question: Moore Company would like to determine the variable utilities rate per direct machine hour in order to estimate cost for August. Relevant information is as
Moore Company would like to determine the variable utilities rate per direct machine hour in order to estimate cost for August. Relevant information is as follows.
| Month | Machine Hours Worked | Utilities Cost |
| April | 4,800 | P4,149 |
| May | 5,200 | 4,300 |
| June | 5,600 | 4,482 |
| July | 6,000 | 4,804 |
Moore anticipates producing 3,800 units in August, with each unit requiring 1.5 hours of machine time. The company uses the high-low method to analyze costs.
a. Calculate the variable and fixed components of the utilities cost.
b. Using the data calculated above, estimate the utilities cost for August.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
