Question: More Info a. Choose the correct project network diagram below. A. B. C. Activity(-ies) c. The critical activities are , so they make up the


More Info a. Choose the correct project network diagram below. A. B. C. Activity(-ies) c. The critical activities are , so they make up the critical path. The entire project will take days to complete. (Enter your response rounded to one decimal place.) d. Every day the project goes on costs the company $5,500 in overhead costs. One of the managers responsible for carrying out activity D feels she can crash the activity by 1 day through the use of overtime. The cost would be only $4,500. Should the company do it? A. Yes, because crashing cost is less than the daily project's cost. B. No, because activity D is not on the critical path. C. No, because crashing cost is more than the dally project's cost. D. Yes, because the total project time will be reduced by 1 day