Question: * * Most importantly needed the AOA or AON * * Construct an Activity - on - Arrow ( AOA ) or Activity - on
Most importantly needed the AOA or AON
Construct an ActivityonArrow AOA or ActivityonNode AON network from the precedence relationships of activities in the project given in the following Table.
Also calculate critical path, and EST and LFT values for each event, and verify floats using spread sheet. Check your critical path
tableActivityDescription,Predecessors,DurationAPreliminary design,BEvaluation of design,CContact negotiations,DPreparation of fabrication plant,AEFinal design,BFFabrication of Product,CGShipment of the Product to owner,B DHField inspection of the Product,C EIInstallation of the Product,FJField painting,FKFinal inspectionapprovalE G I,LProject closeout,H J