Question: Most project resources are negotiated with: Select one: a . Project managers. b . External stakeholders. c . Top management. d . Potential team members.
Most project resources are negotiated with:
Select one:
a
Project managers.
b
External stakeholders.
c
Top management.
d
Potential team members.