Question: Motors are assembled in a process with two resources. The capacities of the resources are 1 . 4 and 1 . 2 motors per minute.

Motors are assembled in a process with two resources. The capacities of the resources are 1.4 and 1.2 motors per minute. Demand occurs at the rate 0.84 motors per minute.
What is the implied utilization (%) of the first resource?