Question: Motors are assembled in a process with two resources. The first resource has a capacity of 6 . 7 motors per hour. The capacity of

Motors are assembled in a process with two resources. The first resource has a capacity of 6.7 motors per hour. The capacity of the second resource is 4.5 motors per hour. Demand for this process is 2.3 motors per hour.
What is the cycle time of this process (in minutes)?
Note: Do not round intermediate calculations. Round your answer to 3 decimal places.