Question: Motul Co. entered into a long-term construction contract for 3 years. Contract price agreed was P8,300,000. The outcome of the contract was estimated reliably.

Motul Co. entered into a long-term construction contract for 3 years. Contract

 

Motul Co. entered into a long-term construction contract for 3 years. Contract price agreed was P8,300,000. The outcome of the contract was estimated reliably. The following data were ascertained for the contract: What is the construction in progress as of 2021? Percentage of Completion 2020 - 30% 2021 - 82.5% Estimated Costs to Complete 2020 - 3,920,000 20211,680,000

Step by Step Solution

3.41 Rating (160 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

To calculate the Construction in Progress as of 2021 youll need to use the Percentage of Completion method This method recognizes revenue and costs on ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Finance Questions!