Question: Motul Co. entered into a long-term construction contract for 3 years. Contract price agreed was P8,300,000. The outcome of the contract was estimated reliably.

Motul Co. entered into a long-term construction contract for 3 years. Contract price agreed was P8,300,000. The outcome of the contract was estimated reliably. The following data were ascertained for the contract: What is the construction in progress as of 2021? Percentage of Completion 2020 - 30% 2021 - 82.5% Estimated Costs to Complete 2020 - 3,920,000 20211,680,000
Step by Step Solution
3.41 Rating (160 Votes )
There are 3 Steps involved in it
To calculate the Construction in Progress as of 2021 youll need to use the Percentage of Completion method This method recognizes revenue and costs on ... View full answer