Question: & Moving to another question will save the response Question 8 If a delay in an activity will not cause a delay to the whole

& Moving to another question will save the
& Moving to another question will save the response Question 8 If a delay in an activity will not cause a delay to the whole project, then this activity CA Has its optimistis time equal to its pessimistic time OB s not on the critical path Has a zero lack time on the critical path the Question with