Question: Moving to another question will save this pon. Question 14 A local project being analyzed by PERT hus 42 activities, 13 of which are on

Moving to another question will save this pon.
Moving to another question will save this pon. Question 14 A local project being analyzed by PERT hus 42 activities, 13 of which are on the critical path. If the expected time along the critical path is 105 days with a project verince of 25, what is the probability that the project will be completed in 95 days or less? Note: Write your answer in whole number percentage 1 Questions Moving to another Gestion will save this response Clown MacBook Air