Question: Moving to another question will save this response. Question 10 (CH6) Consider the following three estimates for the duration of an activity: Optimistic (to) =

Moving to another question will save this
Moving to another question will save this response. Question 10 (CH6) Consider the following three estimates for the duration of an activity: Optimistic (to) = 8 weeks Most likely (tM) - 12 weeks Pessimistic (TP) = 16 weeks Using the triangular distribution, the calculated Expected activity duration (TE) is a. 10.0 weeks. O b. 10.5 weeks. c. 11.5 weeks. O d. 12.0 weeks. A Moving to another question will save this response