Question: Moving to another question will save this response Question 18 of 25 Question 18 4 polis Save Answer The NPV and IRR methods are interrelated
Moving to another question will save this response Question 18 of 25 Question 18 4 polis Save Answer The NPV and IRR methods are interrelated and are often used together to make capital budgeting decisions. The project has the same risk as the firm's average project. Although you don't know the project's initial cost, you have been told that the project has an as of 11.3. Your boss wants to accept the project because the project's IRR exceeds the WACC of 10.0%, blit another manager has mentioned that the NPV should be considered, Although you do not know the value of the project's initial investment, your boss would like you to evaluate a project with the following cash inflows: Year Cash Flow $375,000 2 $500,000 3 $500,000 4 $425,000 You plan to start the calculations by est imating the initial investment using Information available to you IRR is the cost of capital at which NPV equals So Using this and the NPV of the project is umbers only with no Information, the initial investment of the project turns out to be decimals and no periods) 1
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
