Question: Moving to another question will save this response Question 2 of 10 Question 2 4 points Save (CH 7) A project was estimated to cost

Moving to another question will save this
Moving to another question will save this response Question 2 of 10 Question 2 4 points Save (CH 7) A project was estimated to cost AED 1.5M and scheduled to last for 6 months. After three months, what would be the Schedule Variance given the following earned value analysis in AED? TV - AED 650,000; PV = AED 750,000 AC - AED 800,000 a..100,000 b. 100,000 6.-50,000 Od 50,000