Question: & Moving to another question will save this response. Question 10 A work system has five stations that have process times of 5.9.4,9. and 8.

& Moving to another question will save this
& Moving to another question will save this response. Question 10 A work system has five stations that have process times of 5.9.4,9. and 8. What is the bottleneck time? 4 09 18 0 35 07