Question: Moving to another question will save this response. Question 3 0 Forward - pass method and backward - pass method are going to yield different

Moving to another question will save this response.
Question 30
Forward-pass method and backward-pass method are going to yield different critical path resulting in different project completion duration.
a. True
b. False