Question: Moving to another question will save this response. Question 30 An activity has an optimistic time estimate of four days, a most likely time estimate

Moving to another question will save this response. Question 30 An activity has an optimistic time estimate of four days, a most likely time estimate of eight days, and a pessimistic time estimate of fifteen days. The expected duration of this activity is: O A 7.0 days OB.7.5 days OC. 8.0 days O 0.8.5 days
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock