Question: Moving to another question will save this response. Question 30 An activity has an optimistic time estimate of four days, a most likely time estimate

Moving to another question will save this

Moving to another question will save this response. Question 30 An activity has an optimistic time estimate of four days, a most likely time estimate of eight days, and a pessimistic time estimate of fifteen days. The expected duration of this activity is: O A 7.0 days OB.7.5 days OC. 8.0 days O 0.8.5 days

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!