Question: Moving to another question will save this response. Question 7 of 3 6 Question 7 8 . 5 points A project task has an early

Moving to another question will save this response.
Question 7 of 36
Question 7
8.5 points
A project task has an early start time of 3, a late start time of 6, an early finish time of 9, and a late finish time of 12. What is the task's slack?
A.4
B.12
C.0
D.6
E.3