Question: mpany is ordering 12 times per year (75 units each time). There are 250 working days per year, and the lead time is 10 days.

mpany is ordering 12 times per year (75 units

mpany is ordering 12 times per year (75 units each time). There are 250 working days per year, and the lead time is 10 days. en the current policy of ordering 75 units at a time, the total of the annual ordering cost and the annual holding cost is (round your response to the nearest whole number)