Question: MPS is an aggregate plan while SOP is the disaggregated plan. Group of answer choices True False An MPS is frozen in the period between
MPS is an aggregate plan while SOP is the disaggregated plan.
Group of answer choices
True
False
An MPS is frozen in the period between the demand fence and the planning fence
Group of answer choices
True
False
(Hint: Start with a blank MPS record, then input the given numbers. After that, calculate the answers on your table). The sales plan for the MPS calculation of an end-item shows the following numbers for Weeks 1 through 6: 50, 50, 20, 15, 15 and 30.
The beginning inventory is 20, Lot size is 40, and safety stock is 10.
The MPS gives the following figures for Weeks 1, 2 and 3 respectively.
Group of answer choices
40, 40, 40
40, 50, 40
0, 90, 40
40, 0, 40