Question: MPS Record Lot Size: 130 Lead Time: 1 Quantity on Hand (Period 0): 45 Week 1 2 3 4 5 6 7 8 9 10
MPS Record Lot Size: 130 Lead Time: 1 Quantity on Hand (Period 0): 45 Week 1 2 3 4 5 6 7 8 9 10 Forecast 25 25 25 25 20 20 20 20 40 20 Customer 30 20 5 8 2. Orders Projected on-hand 15 120 B 70 50 30 C 120 80 60 inventory MPS 130 130 Quantity MPS 130 130 Start Available- to- 15 A D Promise D What is the Available-to-Promise (ATP) for week 8? (D) 95 10 70 130