Question: Mr. Skillman is aware that if the project does not meet the scheduled deadline, it will cost management $25,000 per day in penalties. With 4

Mr. Skillman is aware that if the project does not meet the scheduled deadline, it will cost management $25,000 per day in penalties. With 4 months to completion, Mr. Skillman realizes the project is running late. Mr. Skillman seeks approval from the Project Sponsor for more money to add human resources. This is an example of _?_.

Group of answer choices

crashing

fast tracking

expert judgment

cost benefit analysis