Question: MRP Analysis (5 points) 1. For the MRP segments, identify the values below for Material A-1. Time in weeks. Finished Product A PO: Product Order

MRP Analysis (5 points) 1. For the MRP segments,
MRP Analysis (5 points) 1. For the MRP segments, identify the values below for Material A-1. Time in weeks. Finished Product A PO: Product Order 0 1 2. 3 5 6 7 4 500 500 350 0 2 3 4 5 6 7 1000 400 1000 400 700 200 ? 1400 400 400 200 Material A-1 GR: Gross Requirement OH: On Hand NR: Net Requirement POR: Planned Order Receipt PO: Purchase Order 600 300 1000 500 500 1000 500 Lead time = 400 X Initial Quantity on Hand = 400 X Lot Size Rule = 400 X Usage = SOO Soo X Beginning stock for the next MRP segment = SOOX