Question: MRP example 2 Complete the MRP record shown in the following table for subassembly # 2 . Use the following assumptions: Lead time for subassembly

MRP example 2
Complete the MRP record shown in the following table for subassembly #2. Use the following assumptions:
Lead time for subassembly #2=2 week:
Lead time for all other parts =1 week
Lot size for subassembly #2=300 units
Lot for lot method is used to determine lot sizes for all other parts