Question: MRP methodology to develop a plan for the next 10 weeks. They've gathered the following information: A l l B C l D According to
MRP methodology to develop a plan for the next 10 weeks. They've gathered the following information:
A
l l
B C
l
D

According to an MRP schedule, which of the following is (are) planned order releases during the next 10 weeks?
I. A planned order release for 170 A's in Week 7.
II. A planned order release for 175 B's in Week 4.
III. A planned order release for 30 C's in Week 3.
| II only | ||
| I, II, and III | ||
| I and II only | ||
| I and III only | ||
| II and III only |
Which of the following is (are) true, concerning week 7 of the MRP schedule?
I. 500 of Item B are ordered (Planned Order Releases).
II. There's a Gross Requirement of 500 for Item D.
III. There is an inventory level of 10 units for Item C throughout that week.
| III only | ||
| I and III only | ||
| II and III only | ||
| I only | ||
| I, II and III |
Current Inventory Records Master Production Schedule Current Inventory Records Master Production Schedule
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts