Question: MRP: *The next five questions involve a full MRP explosion involving two end items, A & B. Each question asks you to complete one of
MRP: *The next five questions involve a full MRP explosion involving two end items, A & B. Each question asks you to complete one of the schedules for parts, A,B,C,D,and E. You should complete the full explosion on a piece of paper before entering your responses for these questions*
Use a lot for lot strategy when placing an order given the following information:
BOM for end item, A. A is made of 2 C's and 1 E.
BOM for end item B. B is made of 3 C's and 1 D.
Inventory Schedule:
| Item | On Hand | Lead time |
| A | 20 | 1 |
| B | 40 | 1 |
| C | 70 | 1 |
| D | 60 | 1 |
| E | 50 | 1 |
MPS:
| Period | 1 | 2 | 3 | 4 |
| Gross Req A | 0 | 80 | 0 | 30 |
| Gross Req B | 0 | 30 | 20 | 70 |
Complete the schedule for item A
|
| 0 | 1 | 2 | 3 | 4 |
| Gross Req |
|
|
|
|
|
| On-hand |
|
|
|
|
|
| Net Req |
|
|
|
|
|
| Planned Order receipt |
|
|
|
|
|
| Planned Order release |
|
|
|
|
2.
Complete the schedule for item B
|
| 0 | 1 | 2 | 3 | 4 |
| Gross Req |
|
|
|
|
|
| On-hand |
|
|
|
|
|
| Net Req |
|
|
|
|
|
| Planned Order receipt |
|
|
|
|
|
| Planned Order release |
|
|
|
|
3.
Complete the schedule for item C
|
| 0 | 1 | 2 | 3 | 4 |
| Gross Req |
|
|
|
|
|
| On-hand |
|
|
|
|
|
| Net Req |
|
|
|
|
|
| Planned Order receipt |
|
|
|
|
|
| Planned Order release |
|
|
|
|
4.
Complete the schedule for item D
|
| 0 | 1 | 2 | 3 | 4 |
| Gross Req |
|
|
|
|
|
| On-hand |
|
|
|
|
|
| Net Req |
|
|
|
|
|
| Planned Order receipt |
|
|
|
|
|
| Planned Order release |
|
|
|
|
5.Complete the schedule for item E
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts