Question: MRP uses infinite loading with setback scheduling in its planning and control of the work necessary to fulfill the MPS. a.True b.False PAC deals with

MRP uses infinite loading with setback scheduling in its planning and control of the work necessary to fulfill the MPS.

a.True

b.False

PAC deals with controlling the activity of delivering a service or making a product.

a.False

b.True