Question: MS 3 0 5 3 - Problem Set # 1 0 Due Date: December 3 , 2 0 2 4 # 1 The manager of
MS Problem Set #
Due Date: December
#
The manager of a local sports club is planning its soccer season. The activities, their immediate predecessors, and the activity time estimates in weeks are as follows.
tableTime weeksActivityDescription,PredecessorsOptim.,Most Likely,Pessim.AMeet with board,BInterviewhire coaches,ACReserve fields,ADCreate schedule,B CEMeet with coaches,BFRegister players,AGOrder uniforms,DHCollect fees,GIOrganize first practice,E F H
a Draw the project network diagram.
b Compute the mean and variance of the duration of each activity. You may do this by hand or by using technology, such as Excel.
c Determine the critical path, the expected project duration, and the variance of the project duration.
d What is the probability that the planning process is completed within weeks?
e What is the probability that the planning process takes longer than weeks?
f If the manager wants a probability of completing the planning process on time, how far ahead of the first practice should they start the project?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
