Question: MS 3 0 5 3 - Problem Set # 1 0 Due Date: December 3 , 2 0 2 4 # 1 The
MS Problem Set #
Due Date: December
#
The manager of a local sports club is planning its soccer season. The activities, their immediate predecessors, and the activity time estimates in weeks are as follows.
a Draw the project network diagram.
b Compute the mean and variance of the duration of each activity. You may do this by hand or by using technology, such as Excel.
c Determine the critical path, the expected project duration, and the variance of the project duration.
d What is the probability that the planning process is completed within weeks?
e What is the probability that the planning process takes longer than weeks?
f If the manager wants a probability of completing the planning process on time, how far ahead of the first practice should they start the project?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock